Table 5.
Additional economic parameters for production system.
| Economic parameter | Technical parameter/decision variable | Value ID | Cost | Unit |
|---|---|---|---|---|
| Investment in connection (well-platform) of vertical/horizontal well | Production/injection flowline | 4″ | 411 | USD/m |
| 6″ | 768 | |||
| 8″ | 1976 | |||
| Riser | 4″ | 879 | USD/m | |
| 6″ | 1513 | |||
| 8″ | 2597 | |||
| Riser and flowline installation | – | 11.70 | USD millions | |
| Investment in drilling and completion of vertical well | Production column | 3″ | 234 | USD/m |
| 4″ | 250 | |||
| 5″ | 270 | |||
| Drilling and completion | – | 20.90 | USD millions | |
| Investment in drilling and completion of horizontal well | Production column | 3″ | 234 | USD/m |
| 4″ | 250 | |||
| 5″ | 270 | |||
| Drilling and completion | – | 21185 | USD/m horiz | |
| – | 25.66 | USD millions | ||
| Investment in recompletion of vertical well | Production column | 3″ | 29 | USD/m |
| 4″ | 45 | |||
| 5″ | 65 | |||
| Workover | – | 7.86 | USD millions | |
| Additional investment in connection for Artificial-Lift | Injection flowline 4″ | – | 411 | USD/m |
| Riser 4″ | – | 879 | USD/m |